If you’ve never met a GMP contract, let
me provide an introduction. GMP is a handy tool put to good use by many contractors.
Back in July of 2010, I explained why
home improvement contractors in six states (CA, IL, MA, NV, PA and TN) use GMP contracts.
In those states, time & material contracts aren't legal for most residential
work and can't be enforced. That makes GMP contracts an obvious choice. What I didn’t
explain back in 2010 was how to write a GMP contract. So here goes.
Think of GMP as a hybrid T&M contract.
You invoice for time and materials but also have a guaranteed maximum price. A deal
like that meets state requirements, no matter where you build.
Here’s how to draft a good GMP contract,
step-by-step:
-
Define the contract price. That’s your cost plus a fee. Your fee could be a percentage of all other costs or a lump sum or a set amount per week or month.
- Define your cost. That’s usually labor, materials, subcontracts, equipment, supervision and overhead. Make your definitions tight enough so there’s no room for quibbling. More about this later.
- Decide what records you’ll provide with each invoice. A spreadsheet with receipts and timecard backup is best.
- Set a guaranteed maximum price in dollars and cents – usually about 25% more than what you would bid on a fixed price basis.
- Finally, decide how any savings will be split. Fifty-fifty is a good starting point for negotiations. If actual job cost is less than the GMP, savings are split between owner and contractor by this formula.
-
What’s included? The answer: Everything reasonably necessary to finish the job. Subpart 31.201-3 of the Federal Acquisition Regulations has the best definition I know for “reasonable” in a construction setting.
- Labor cost includes wages plus taxes, insurance and benefits based on payroll. If you want, list hourly costs for each trade and specialty. Is overtime allowed? At what rate?
- Material and subcontract costs are what you pay after any discount. Remember, under a GMP contract, you have an incentive to keep costs down.
- Equipment costs should include your rental expense and a billing rate for any contractor-owned equipment on the job.
- Supervision expense should include only time a supervisor spends on the job site.
- Overhead expense is usually an estimate expressed as a cost per week or month.
Not every job or client is right for
GMP contracting. But if you use Construction Contract Writer, it’s easy to offer
alternate contracts – both a GMP and a fixed price contract. Let the owner decide
what’s best. An owner who has confidence in your work and understands the advantage
of risk-sharing will probably choose the GMP deal.