Vermont has several financial assistance programs designed to help low-income, elderly or disabled residents make residential repairs. Alana Brault qualified for one of these programs. She selected Polli Construction's "Rot Doctor" to remove and replace her front door and repair rot around the frame and subfloor. The contract price was $14,312 including labor, materials and the permit. The contract required Polli to "assess the framing under the floor” but excluded any repair to floor framing. According to the contract, "any work outside the scope above will be completed on a time and material basis." Ms. Brault signed the contract.
In the words of Superior Court judge Samuel Hoar, Jr:
One day into the job, one of Polli's worker's advised Ms. Brault that Polli had discovered rot below the subfloor. Polli refused to continue work unless Ms. Brault signed a change order for additional work on a time and materials basis. At this point, Ms. Brault had no real choice; the entry door and framing had been removed, leaving her home open to the elements, protected only by a makeshift tarp shed. The Polli worker told her, "don't worry; it probably won't cost much more." On the strength of this assurance, and in the face of Polli's threat to walk away from the job if she refused to sign the change order, Ms. Brault reluctantly signed off.
Polli’s final bill was $22,643.47. That was $8,331 more than the signed contract. Vermont’s granting agency paid $16,400 on Ms. Brault’s behalf. Polli filed suit against Brault to collect the remaining balance, $6,243.47
How Would You Decide This Case?
Before deciding, notice three points:
- Polli Construction refused to continue unless Ms. Brault signed the change order.
- During negotiations, the front door was off Ms. Brault’s home.
- Polli’s crew told Ms. Brault, “Don’t worry, It probably won’t cost much more.”
The court ruled there were two contracts: (1) The original $14,312 deal and (2) The time and material addition. The first of these was freely entered into by both sides and was fully enforceable. The second was not enforceable for two reasons:
- Improper pressure during any bargaining process is duress. An improper threat renders any agreement voidable by the victim. Here Polli threatened to walk off the job, leaving Ms. Brault’s home open to the elements if she didn’t sign.
- The doctrine of equitable estoppel. Polli’s worker represented that the additional work wouldn’t cost much more. Polli Construction must have known this was not true. Polli must also have known Ms. Brault would rely on that assurance. Ms. Brault signed the second agreement relying on the statement by Polli’s tradesman. Polli Construction can’t now deny what their tradesman represented.
On the time and material contract, the court concluded Polli was estopped from recovering more than the “won’t cost much more” promised. Polli had been paid a total of $16,400. Payment of $2,088 on the second contract fit the court’s definition of “won’t cost much more”. Polli’s claim for the last $6,243.47 was denied.
Lessons from Polli vs. Brault
- Don’t give an impression that you’ll walk off a job if the owner won’t sign a change order.
- Caution subs and tradespeople to avoid any discussion of costs with an owner.
Polli Construction didn’t collect the last $6,243.27. But Polli’s contract wasn’t the problem. The signed agreement left no doubt about what was included and excluded. That's a good contract. To draft letter-perfect contracts for any type of job in any state, have a look at Construction Contract Writer. The trial version is free.
