Andrew and Ginger McBride selected Rafael Lara Construction to build their new home in Monroe, Louisiana. Plans and specs were prepared by a local architect and incorporated into the contract. Laura signed the agreement in August 2018 and started work the following October. As in most construction projects, there were problems:
Conflict started with the floor deck. Lara installed Weyerhaeuser Gold. McBride wanted Advantech. Job specs didn’t specify either type of decking. Advantech wasn’t in stock at the local supplier. To satisfy McBride, Lara offered to double the decking at no extra charge. McBride agreed.
Lara installed 7/16” OSB roof deck. Job specs called for 5/8” foil-backed deck. True, 5/8” roof deck is better for a low-slope roof when snowpack is expected. But snow load isn’t an issue in Monroe Louisiana. And the McBride’s roof was steep pitch. The architect confirmed that 7/16” roof deck was consistent with his specs and was OK under the building code
Lara used 26-gauge galvanized aluminum roof flashing where roofing met brick siding. He used 26-gauge powder-coated aluminum trim coil for exterior flashing. Specs required 26-gauge galvanized steel flashing. Laura likes aluminum flashing because it doesn’t rust. Plus, the powder coated aluminum flashing matched the eaves and soffit.
According to McBride, stone veneer on the front façade had gaps. Several stones had fallen out. Some stones were only pressed in the mortar. Other sections had no mortar. Lara agreed the stone veneer wasn’t done. But installation met the manufacturer's specs. Lara planned to make final repairs as a “punch list” item.
Ten of the 12 windows were hard to open and close. A window sales rep told McBride the windows had not been installed properly. The window cavity was too small. But a rep for the manufacturer found only a few windows that were “closing tight”. Replacing the window sashes would solve the problem. Cost would be four or five hundred dollars. But the manufacturer offered to replace binding sash at no charge as a courtesy to McBride.
Job specs showed 3/8” wood paneling in the garage. Wood paneling in a garage won’t pass inspection. Lara recommended drywall for the garage. McBride agreed if the drywall was moisture-resistant “green rock”. Lara hung greenboard, but only on one wall. McBride didn’t like that.
Before flashing was installed, McBride spotted roof leaks in three areas: (1) Between the garage and house below the laundry room; (2) In front of the dormer over the office; and (3) Over the back side of the garage. Once flashing was installed, the toeboard sealed and a dormer window reset, Lara tested for leaks with a hose pressure nozzle. Then he cut holes in the wallboard and probed for moisture with a paper towel. Lara’s project manager used a moisture meter to check for signs of leakage. The framing was dry.
Despite not finding any moisture in the framing, Lara scheduled a sheet metal company to install extra flashing in roof valleys. Because rain was expected before the extra flashing could be installed, Lara tacked up temporary hog troughs (large metal sheets) in the roof valleys.
That was the last straw. McBride shut the job down and had his attorney send a list of grievances to Lara. Among other issues, McBride demanded replacing 7/16” roof deck with 5/8” decking. Lara responded ten days later. He denied nearly all the defects and offered to resume work. McBride took that as a hard “no”. He filed suit for breach of contract. That was 2019. The case was tried in February 2024.
The trial court awarded McBride $21,860 after offsets to Lara. Both McBride and Lara moved for a new trial. After a hearing on the motions, the trial court issued its second judgment, reducing the total award to McBride to $12,160. McBride filed an appeal. On October 22, 2025, appellate court for Louisiana’s Second Circuit confirmed the lower court decision. Lara was out $12,160.
But Notice This
Lara worked on the McBride job for 6 months. But the case of McBride v. Raphiel Lara Construction dragged through Louisiana courts for over 6 years. Louisiana does not award attorney fees in cases like this. But my guess is that attorney fees approached (or maybe even exceeded) the cost of construction. That’s not a happy prospect for any home builder.
What could Lara have done to avoid 6 years in court? Lara did what he could to satisfy McBride. But I have three clear observations:
First, the contract could have required arbitration. Courts won’t touch a dispute if the contract requires arbitration. At one point during the six years, Lara suggested mediation. That’s too late. Once work starts, any agreement to binding arbitration has to be mutual.
Second, every change in job specs, every agreement that resolves some issue, needs a written change order. On this job, grievances continued to accumulate. Any time you reach a new agreement, document it. Put a price on the change and get a signature. That draws a line. It’s a meeting of the minds. A fresh beginning.
Third, any time you anticipate problems with a client, add a termination clause to the contract. An owner who shuts down the job owes you for all work done to date of termination plus a proportionate share of your overhead and profit. Because work was never completed, Lara didn’t collect any share of his overhead and profit.
When you sense acrimony might derail a job, your best protection is a good contract. No matter the type of work or the job site, there’s no better contract drafting tool than Construction Contract Writer. The trial version is free.
